AGENDA
Semi-Monthly Meeting – Full Council
Tuesday, November 1, 2022; 6:00 p.m.

Administration Building, Conference Room A
One Capitol Hill, Providence, RI


Approval of the minutes of the previous meeting — Tuesday, October 11, 2022

Subcommittee Reports

Staff Reports

Review and Action regarding Application requiring Public Hearing and Special Exception:

2021-07-005 REVOLUTION WIND -- Two submarine export transmission cables (275 kilovolt high voltage alternating current (AC)) have been proposed for the project. Each cable measures approximately 23 miles in length and has been proposed to be installed in CRMC Type 4 and 6 Waters in Rhode Island Sound and the West Passage of Narragansett Bay, making landfall at the Quonset Business Park, North Kingstown. The export cable will cross an Area of Particular Concern as identified by Ocean Special Area Management Plan § 11.10.2 and will require a Special Exception under Coastal Resources Management Program Section 1.1.8.

The cables will be installed at a target burial depth of 4-6 feet (or deeper) below the seabed, which will create a total estimated disturbance of approximately 730 acres within state waters. Secondary cable protection in the form of rock bags, concrete mattresses, and/or rock berms may be used where the target burial depth cannot be achieved.

The export cables will make landfall at the Quonset Business Park, the heavily Industrial waterfront via horizontal directional drilling, which will require the construction of two offshore exit pits.

After joining with the export cables, the Onshore Transmission Cable will follow Circuit Drive northwest to 135 Circuit Drive, where it will cross this property north of the existing driveway and cross the property in a north-northwest direction until reaching the property owned by Quonset Development Corporation. Here the cable will continue north until reaching 101 Circuit Drive. The cable will then continue north across 101 Circuit Drive and 75 Circuit Drive within the existing paved access road to the existing Davisville Substation. At the Davisville Substation, the cable continues west, parallel to the northern property boundary before reaching The Narragansett Electric Company's parcel. After crossing, the cable enters the Onshore Substation tying into the proposed access road. The total cable length is approximately one mile.

 

CALENDAR INDEX

Stedman Government Center
Suite 116, 4808 Tower Hill Road, Wakefield, RI 02879-1900
Voice 401-783-3370 • Fax 401-783-2069 • E-Mail cstaff1@crmc.ri.gov

RI SealRI.gov
An Official Rhode Island State Website